Waitsia Stage 1: Production

Production continues. Xyris Production Facility capacity is 30 Terajoules (TJ)/day.

Ongoing

Waitsia Stage 2: Construction of Waitsia Gas Plant

Waitsia Gas Plant Facility will have 250TJ/day capacity.

Scheduled for completion mid-2024.

Waitsia Gas Field: Waitsia-05 through Waitsia-10

Wells Waitsia-05 through Waitsia-10 drilled, completed & tested.

Activities completed in 2022.

Waitsia Gas Field: Waitsia-11

Waitsia-11 well drilled, completed and tested.

Activities completed in 2023.

Waitsia Gas Field: Gynatrix-01

Gynatrix-01 well completion & well testing activities.

Completion concluded; Clean Up and Testing anticipated for 8 February.

Waitsia Gas Field: Waitsia-12 through Waitsia-19

Wells Waitsia-12 through Waitsia-19:
Site preparation & well pad construction

Mid-April 2024 anticipated start

Waitsia Gas Field: Waitsia-12 through Waitsia-19

Wells Waitsia-12 through Waitsia-19: Drilling activities

July 2024 anticipated start

Flowline and hub construction activities

Connecting to existing gas gathering system

Q3 2024 approximate timing

EP413: Arrowsmith

Airborne Surveys - AGG and Apis AMAG (Part 1)

Completed mid-December 2023.

EP413: Arrowsmith

Airborne Surveys - Apis AMAG (Part 2)

Anticipated to commence 19 January 2024.
Duration ~7-10 days.

EP455, L4, L5: Stockyard

2D Seismic Survey

Scheduled between January and June 2024

L1 wells: Dongara 21A, Dongara-31, Dongara-36, Dongara-37 and Senecio-01

Plug & Abandonment activities

Planned for Q1/Q2 of 2024, ~25 days duration per well

L2 wells: Centella-01, Snottygobble-01 and Eremia-01.

Plug & Abandonment activities

Planned for Q1/Q2 of 2024, ~25 days duration per well

L2 well: Hovea-08

Plug & Abandonment activities

Working toward mid-2024 complex P&A intercept well.

EP413 well: Arrowsmith-02

Plug & Abandonment activities

Planned for Q1/Q2 of 2024, ~25 days duration per well

L4/L5 well: Woodada-12 and Woodada-15

Plug & Abandonment activities

Planned for Q1/Q2 of 2024, ~25 days duration per well

Dongara Production Facility

In 'Care and Maintenance'. Operations have ceased.

Processing equipment was decommissioned, removed and recycled early in 2021.

Hovea Production Facility

In 'Care and Maintenance'. Operations have ceased.

Processing equipment was decommissioned, removed and recycled early in 2021.

Woodada Production Facility

In 'Care and Maintenance'. Operations have ceased.

Processing equipment was decommissioned, removed and recycled early in 2021.