Schedule of Activities
Our projects in the Perth Basin cover the various stages of project life-cycle. Following are anticipated timings for key activities. Please note, timings provided are indicative only and subject to change.
Waitsia Stage 1: Production
Production continues. Xyris Production Facility capacity is 30 Terajoules (TJ)/day.
Ongoing
Waitsia Stage 2: Construction of Waitsia Gas Plant
Waitsia Gas Plant Facility will have 250TJ/day capacity.
Scheduled for completion mid-2024.
Waitsia Gas Field: Waitsia-05 through Waitsia-10
Wells Waitsia-05 through Waitsia-10 drilled, completed & tested.
Activities completed in 2022.
Waitsia Gas Field: Waitsia-11
Waitsia-11 well drilled, completed and tested.
Activities completed in 2023.
Waitsia Gas Field: Gynatrix-01
Gynatrix-01 well completion & well testing activities.
Completion concluded; Clean Up and Testing anticipated for 8 February.
Waitsia Gas Field: Waitsia-12 through Waitsia-19
Wells Waitsia-12 through Waitsia-19:
Site preparation & well pad construction
Mid-April 2024 anticipated start
Waitsia Gas Field: Waitsia-12 through Waitsia-19
Wells Waitsia-12 through Waitsia-19: Drilling activities
July 2024 anticipated start
Flowline and hub construction activities
Connecting to existing gas gathering system
Q3 2024 approximate timing
EP413: Arrowsmith
Airborne Surveys - AGG and Apis AMAG (Part 1)
Completed mid-December 2023.
EP413: Arrowsmith
Airborne Surveys - Apis AMAG (Part 2)
Anticipated to commence 19 January 2024.
Duration ~7-10 days.
EP455, L4, L5: Stockyard
2D Seismic Survey
Scheduled between January and June 2024
L1 wells: Dongara 21A, Dongara-31, Dongara-36, Dongara-37 and Senecio-01
Plug & Abandonment activities
Planned for Q1/Q2 of 2024, ~25 days duration per well
L2 wells: Centella-01, Snottygobble-01 and Eremia-01.
Plug & Abandonment activities
Planned for Q1/Q2 of 2024, ~25 days duration per well
L2 well: Hovea-08
Plug & Abandonment activities
Working toward mid-2024 complex P&A intercept well.
EP413 well: Arrowsmith-02
Plug & Abandonment activities
Planned for Q1/Q2 of 2024, ~25 days duration per well
L4/L5 well: Woodada-12 and Woodada-15
Plug & Abandonment activities
Planned for Q1/Q2 of 2024, ~25 days duration per well
Dongara Production Facility
In 'Care and Maintenance'. Operations have ceased.
Processing equipment was decommissioned, removed and recycled early in 2021.
Hovea Production Facility
In 'Care and Maintenance'. Operations have ceased.
Processing equipment was decommissioned, removed and recycled early in 2021.
Woodada Production Facility
In 'Care and Maintenance'. Operations have ceased.
Processing equipment was decommissioned, removed and recycled early in 2021.